March 18, 2026
1. Upcoming Work: FSR Bridge Replacement at Catiline Creek, with Temporary Bridge and Bypass
Location: 7.5 km
Dates:
- The updated window for the bridge replacement is Mid April – Mid June 2026.
- The temporary bridge is anticipated to be in place late March
- Traffic may be directed to the bypass from approximately April 1, 2026.
- Exact timing remains to be determined.
What’s happening:
- Traffic will be rerouted to a temporary crossing of Catiline Creek to accommodate the excavation of the creek, and installation of a new permanent bridge.
- A temporary bypass road and temporary bridge will be in place starting from approximately April 1. The bypass will be located just above the existing bridge in the FSR right of way.
- No traffic delays are anticipated.
Who is involved:
- The new permanent bridge is being installed by the Ministry of Forests.
- The creek excavation is by the SLRD’s contractors Coastal Mountain Excavations Ltd. (CME) as part of the Catiline Creek Debris Flow Mitigation Project.
- The temporary bypass and bridge will be put in place by CME
2. Increased Construction Traffic on FSR around Lillooet Lake Estates
Location: 7.5 km
Dates: February 2026 through to end of project.
Hours: Monday to Saturday, 7 AM to 5 PM.
What’s happening:
Construction of the Catiline Creek debris flow structure at Lillooet Lake Estates at 7.5 km. Construction activities including excavation of the creek channel and berm construction will be happening near the FSR.
What to expect:
- Rock trucks hauling excavated materials for berm construction beside Catiline Creek (7.5 km)
- Increased industrial traffic, with contractors’ vehicles and equipment in the area
- Additional traffic control measures including signage
Safety reminders
- Follow the direction of flaggers and signage, and drive with caution.
- Give trucks extra space, especially on hills and corners.
- Avoid stopping within signed work zones unless directed.
March 12, 2026
Updates will be provided when new information is available.
1. Upcoming Work: FSR Bridge Replacement at Catiline Creek, with Temporary Bridge and Bypass
Location: 7.5 km
Dates:
- The updated window for the bridge replacement is Mid April – Mid June 2026.
- The temporary bridge is anticipated to be in place late March
- Traffic may be directed to the bypass from approximately April 1, 2026.
- Exact timing remains to be determined.
What’s happening:
- Traffic will be rerouted to a temporary crossing of Catiline Creek to accommodate the installation of a new permanent bridge over the recently excavated debris flow mitigation channel.
- The Catiline Creek FSR bridge at 7.5 k on the In-SHUCK-ch FSR is being replaced
- A temporary bypass road and temporary bridge will be in place starting from approximately April 1. The bypass will be located just above the existing bridge in the FSR right of way.
- No traffic delays are anticipated.
- More information including updated timing and what to expect will be provided when available.
Who is involved:
- The new permanent bridge is being installed by the Ministry of Forests.
- The temporary bypass and bridge will be put in place by the SLRD’s contractors Coastal Mountain Excavations Ltd. (CME) as part of the Catiline Creek Debris Flow Mitigation Project.
2. Short‑Distance Hauling on FSR
Location: 6.0 km to 7.5 km
Dates: now until Friday March 13, 2026
Daily Hours: Monday to Friday, 7 AM to 5 PM.
What’s happening:
Hauling will take place over a short stretch of the FSR. Trucks will move fill from the Catiline Creek Debris Flow Mitigation project site at 7.5 km to a road realignment project site at 6.5 km. The road realignment project is being managed by the Ministry of Forests.
What to expect:
- High volume of industrial traffic from 6.0 km to 7.5 km
- Loaded highway rock trucks on the FSR. Trucks will be loaded travelling from 7.5 km to 6.5 km, returning empty.
- Additional traffic control including flaggers and signage
Safety reminders
- Follow the direction of flaggers and signage, and drive with caution.
- Give trucks extra space, especially on hills and corners.
- Avoid stopping within the signed work zone unless directed.
3. Increased Construction Traffic on FSR around Lillooet Lake Estates
Location: 7.5 km
Dates: February through to end of project.
Hours: Monday to Friday, 7 AM to 5 PM.
What’s happening:
Construction of the Catiline Creek debris flow structure at Lillooet Lake Estates at 7.5 km. Construction activities including excavation of the creek channel and berm construction will be happening near the FSR.
What to expect:
- Rock trucks hauling excavated materials for berm construction beside Catiline Creek (7.5 km)
- Increased industrial traffic, with contractors’ vehicles and equipment in the area
- Additional traffic control measures including signage
Safety reminders
- Follow the direction of flaggers and signage, and drive with caution.
- Give trucks extra space, especially on hills and corners.
- Avoid stopping within signed work zones unless directed.
More information including updated timing and what to expect will be provided when available.
February 11, 2026
Updates will be provided when new information is available.
1. Short‑Distance Hauling on FSR
Location: 6.0 km to 7.5 km
Dates: February 17 to approximately March 13, 2026
Daily Hours: Monday to Friday, 7 AM to 5 PM.
What’s happening:
Hauling will take place over a short stretch of the FSR. Trucks will move fill from the Catiline Creek Debris Flow Mitigation project site at 7.5 km to a road realignment project site at 6.5 km. The road realignment project is being managed by the Ministry of Forests.
What to expect:
- High volume of industrial traffic from 6.0 km to 7.5 km
- Loaded highway rock trucks on the FSR. Trucks will be loaded travelling from 7.5 km to 6.5 km, returning empty.
- Additional traffic control including flaggers and signage
- Week 1 from February 17 to 20: Short holds up to 15 minutes at 6.5 km to facilitate trucks turning around on the FSR.
- Weeks 2 to 4 from February 23 – March 13: Longer holds up to 1 hour may be required at 6.5 km as work progresses. If 1 hour holds are implemented, openings will be at the top of each hour.
Safety reminders
- Follow the direction of flaggers and signage, and drive with caution.
- Give trucks extra space, especially on hills and corners.
- Avoid stopping within the signed work zone unless directed.
2. Increased Construction Traffic on FSR around Lillooet Lake Estates
Location: 7.5 km
Dates: February through to end of project.
Hours: Monday to Friday, 7 AM to 5 PM.
What’s happening:
Construction of the Catiline Creek debris flow structure at Lillooet Lake Estates at 7.5 km. Construction activities including excavation of the creek channel and berm construction will be happening near the FSR.
What to expect:
- Rock trucks hauling excavated materials for berm construction beside Catiline Creek (7.5 km)
- Increased industrial traffic, with contractors’ vehicles and equipment in the area
- Additional traffic control measures including signage
3. Upcoming Work: FSR Bridge Replacement at Catiline Creek, with Temporary Bridge and Bypass
Location: 7.5 km
Dates: The window for this work is between April 1 and July 1 2026. Exact timing remains to be determined.
What’s happening:
The Catiline Creek FSR bridge at 7.5 k on the In-SHUCK-ch FSR is being replaced. The bridge replacement is being carried out by the Ministry of Forests.
To maintain traffic flow on the FSR a temporary bypass and bridge will be put in place. The temporary bypass and bridge will be put in place by the SLRD’s contractors Coastal Mountain Excavations Ltd. (CME).
More information including updated timing and what to expect will be provided when available.
January 26, 2026 update - At this time we do not anticipate any scheduled closures of the Forest Service Road (FSR) related to project work. However there will be increased activity on and around the FSR in 2026, including the following:
- Winter 2025/2026 - Logging activities began as of October 14, 2025. Hauling of logs started in January.
- Spring 2026 - Catiline Creek bridge replacement. A temporary bypass and bridge will be in place during the bridge replacement at Catiline Creek by Ministry of Forests.
Expect the following activity throughout the project (October 2025 – Winter 2026):
- Trucks hauling excavated materials on the road between 6.5 km and 16 km throughout the project. Hauling of excavated materials will being in February.
- Traffic control personnel and signage on roads throughout the duration of the project
Timing for the above activities remains to be determined. More information will be provided when available.
January 7, 2026 update - At this time we do not anticipate any scheduled closures of the Forest Service Road (FSR) related to project work. However there will be increased activity on and around the FSR in 2026, including the following:
- Winter 2025/2026 - Logging activities began as of October 14, 2025. Hauling of logs will begin in January.
- Spring 2026 - Catiline Creek bridge replacement. A temporary bypass and bridge will be in place during the bridge replacement at Catiline Creek by Ministry of Forests.
Expect the following activity throughout the project (October 2025 – Fall/Winter 2026):
- Trucks hauling excavated materials on the road between 6.5 km and 16 km throughout the project. Hauling of excavated materials will being in February.
- Traffic control personnel and signage on roads throughout the duration of the project
Timing for the above activities remains to be determined. More information will be provided when available.
December 23, 2025 update - At this time we do not anticipate any scheduled closures of the Forest Service Road (FSR) related to project work. However there will be increased activity on and around the FSR in 2026, including the following:
- Winter 2025/2026 - Logging activities began as of October 14, 2025. Timing for hauling of logs is to be determined.
- Spring 2026 - Catiline Creek bridge replacement. A temporary bypass and bridge in place during the bridge replacement at Catiline Creek by Ministry of Forestry.
Expect the following activity throughout the project (October 2025 – Fall/Winter 2026):
- Trucks hauling excavated materials on the road between 6.5 km and 16 km throughout the project.
- Traffic control personnel and signage on roads throughout the duration of the project
Timing for the above activities remains to be determined. More information will be provided when available.
November 19, 2025 update - Notice of planned work at 7.5km on the In-SHUCK-ch FSR.
Tree felling is planned beside the In-SHUCK-ch FSR and the BC Hydro lines from Wednesday November 26 to Friday December 5.
- Traffic control will be in place on the FSR during this time. Anticipate minor delays. Please obey signage and follow directions.
October 6, 2025 update - At this time we do not anticipate any scheduled closures of the Forest Service Road (FSR) related to project work. However there will be increased activity on and around the FSR, including the following:
- Fall 2025 - Logging activities have begun as of October 14, 2025. Timing for hauling of logs is to be determined.
- Spring 2026 - Catiline Creek bridge replacement. A temporary bypass and bridge in place during the bridge replacement at Catiline Creek by Ministry of Forestry.
Expect the following activity throughout the project (Fall 2025 – Winter 2026):
- Trucks hauling excavated materials on the road between 6.5 km and 16 km throughout the project.
- Traffic control personnel and signage on roads throughout the duration of the project
Timing for the above activities remains to be determined. More information will be provided when available. For more on conditions on the In-SHUCK-ch Forest Service Road, please visit the FSR Conditions in the Sea to Sky District website.